Over its lifetime, a building costs far more to operate than to build. Yet at handover the operator still often receives O&M manuals made of hundreds of PDFs, drawings of uncertain status and product sheets that cannot be linked to a specific asset. Much of the information produced during design and construction is lost precisely when it becomes most useful.
BIM can prevent that loss, on one condition: planning for operation from the design stage, not three weeks before handover.
What the operator really needs from the model
A facilities manager does not need the geometry of every bolt. They need to find quickly:
- the assets to maintain, each with a unique tag and located by building, level and room;
- their useful attributes: manufacturer, model, rating, commissioning date, warranty;
- the related documents: data sheets, O&M instructions, test certificates, maintenance contracts;
- room areas and uses, for space management and cleaning contracts;
- plant access routes and the clearances required for maintenance.
Anything outside this list makes the model heavier without helping operations. The job is to choose, not to fill in everything.
Defining information needs early
The process starts with a question to the client and their operator: what information do you want on handover day, and in which system? The answer goes into the client’s information requirements, then into the modelling standards:
- the asset families concerned (HVAC, plumbing, electrical, fire safety, lifts and so on);
- for each, the attributes required and the stage at which they must be populated;
- a common asset coding scheme, compatible with the operator’s CAFM system;
- the exchange format, for example IFC complemented by a structured COBie spreadsheet where the operator’s tools support it.
This takes a few days at the start of a project. Catching up at the end of construction takes weeks, and the result is rarely reliable.
From coordination model to asset information model
The coordination model is used to align the trades during design and construction. It does not automatically become an asset information model. To do so, it has to be updated with what was actually installed (as-built), then enriched with data for the equipment installed rather than the equipment specified.
This is often where the process breaks: contractors deliver their data late, in different formats, and nobody is responsible for checking it. Assigning that check in the BIM Execution Plan, with verification points before handover, makes a real difference.
The link with CAFM
The value of an asset model depends on how well it feeds the tools the operator already uses: CAFM, space management, building management systems. A model opened once and then forgotten brings almost nothing. An asset register imported cleanly into the CAFM system, with the right codes and documents, saves time on every intervention.
Common mistakes
- Asking for “all the data” without saying which, which produces models that are both heavy and incomplete.
- Letting each contractor choose its own coding.
- Leaving operational needs until the end of construction.
- Forgetting to decide who will update the model after later alteration works.
Where to start
On a first project, the scope can be limited to the assets that weigh most in maintenance, often HVAC, domestic hot water, electrical distribution and fire safety, aiming for a clean handover rather than an exhaustive one. Our BIM management and consultancy services cover this set-up, from drafting information requirements to checking deliverables before handover. The method is detailed on our Expertise page.