01A duct running into a downstand beam
THE PROBLEM
A large supply duct crosses a downstand beam in the ceiling void.
THE RISK
Lost ceiling height, or a late penetration through a load-bearing element.
HOW TO SPOT IT
Duct / structure detection with an insulation clearance, then a section at the crossing point.
THE RESOLUTION
Compare an offset below the beam, a penetration approved by the structural engineer, or a switch to a flat-oval duct.
WHAT CLOSES IT OUT
Dimensioned coordination section, approved opening request, decision note.
CASE 02 · POWER × HVAC
02Cable trays and ductwork at the same level
THE PROBLEM
Power cable trays and ventilation ductwork cross with no defined layering order.
THE RISK
Cables cannot be pulled, access is blocked, safety clearances are not met.
HOW TO SPOT IT
Zone-by-zone layering review in the federated model, clearance checks between services.
THE RESOLUTION
Set a height rule for each trade and dedicated crossing zones, then have the routes realigned.
WHAT CLOSES IT OUT
Layering rule issued, typical sections, BCF issues assigned.
CASE 03 · OPENINGS
03Missing or misplaced builder's work openings
THE PROBLEM
A wall penetration does not appear on the builder's work drawings issued to the frame contractor.
THE RISK
Core drilling after the pour, or even structural remedial work and delay.
HOW TO SPOT IT
Automatic listing of penetrations by level, compared with the openings drawn.
THE RESOLUTION
Consolidated builder's work drawings approved before the pour, cross-checked by the structural engineer.
WHAT CLOSES IT OUT
Revised builder's work drawings, approval schedule, tracking of discrepancies.
CASE 04 · TERMINALS × ARCHITECTURE
04Terminals that do not suit the architecture
THE PROBLEM
A diffuser or grille lands on a ceiling grid joint or in a glazed area.
THE RISK
Ceilings or terminals reworked, architectural finish compromised.
HOW TO SPOT IT
Overlay of terminals and the ceiling grid, review with the architect.
THE RESOLUTION
Move the terminals onto the grid, adapt the connecting ductwork, approve the ceiling layout.
WHAT CLOSES IT OUT
Coordinated reflected ceiling plan, architect's approval.
CASE 05 · CEILINGS
05Ceilings, lights, sprinklers and detectors
THE PROBLEM
Light fittings, sprinkler heads, detectors and diffusers compete for the same ceiling tile.
THE RISK
Fire safety non-compliance, rework of installed items at the end of the job.
HOW TO SPOT IT
Ceiling grid check against regulatory distances and setting-out constraints.
THE RESOLUTION
A single ceiling layout combining lighting, HVAC and fire safety, agreed with each trade.
WHAT CLOSES IT OUT
Coordinated ceiling layout, open-issues list by trade.
CASE 06 · ENVELOPE
06Façade, openings, structure and waterproofing
THE PROBLEM
Curtain wall brackets cannot find proper bearing on the slab edge.
THE RISK
Waterproofing defects, inserts to be redone, delay to the building envelope.
HOW TO SPOT IT
Review of façade / frame interface details and installation tolerances.
THE RESOLUTION
Position inserts and brackets early, coordinate the sequence of façade and waterproofing works.
WHAT CLOSES IT OUT
Approved interface details, cast-in insert drawings, façade / frame register.
CASE 07 · HEIGHTS
07A services corridor that is too low
THE PROBLEM
The stack of services exceeds the depth available between slab and ceiling.
THE RISK
Clear height not compliant, or services that cannot be installed.
HOW TO SPOT IT
Systematic sections at the densest points, height check by zone.
THE RESOLUTION
Rank the services, reroute some of them, agree the ceiling height with the design team.
WHAT CLOSES IT OUT
Coordination sections at critical points, formal decision record.
CASE 08 · CONSISTENCY
08Models, drawings and site drifting apart
THE PROBLEM
An issued drawing no longer matches the model, or a site change is not recorded.
THE RISK
Work carried out on an out-of-date basis, clashes reappearing during installation.
HOW TO SPOT IT
Check of revisions and dates in the CDE, model / issued-drawing comparison.
THE RESOLUTION
A single issue procedure, a consistency check before each approval, models kept up to date.
WHAT CLOSES IT OUT
Revision tracking schedule, issue procedure.