A missed builder’s work opening rarely costs much at the time. It costs when a cast wall has to be core-drilled, the penetration approved by the structural engineer, a service rerouted or remedial work awaited. Managed properly, openings are one of the most tangible gains of coordination.
Why openings cause problems
Services are often sized after the structure. Builder’s work drawings issued to the frame contractor therefore have to anticipate routes that are still moving, on deadlines set by the pour programme. The difficulties always recur in the same places: wall and slab penetrations, risers, plant rooms, crossings under downstand beams.