Plant space, ceiling voids, principal penetrations and openings: how to bring structure and MEP together from early stage to construction.

Clashes between structure and services in a federated model

Most costly conflicts in a building sit at the interface between structure and building services: a duct running into a beam, a gravity drain with no possible fall, a riser too small for the equipment selected. Coordinating the two requires a method, because they move at different speeds and under different constraints.

Two programmes that do not overlap

The structure is fixed early, because pours do not wait. Services firm up late, as equipment is selected. Coordination has to make these programmes converge: freeze early the penetrations the structure needs, without forcing the trades into choices they cannot yet make.

What to secure first

  • Plant room and riser footprints.
  • Ceiling void depths under the lowest beams.
  • Principal penetration zones through walls and downstands.
  • Loads of heavy plant and their supports.
02 —

A three-step method

01

Early-stage coordination

At design stage, work with assumed sizes for main ducts, containment and pipework. Check they pass under or through the structure, and agree principal opening zones with the structural engineer.

02

Targeted clash detection

At construction stage, run structure-against-trade tests with tolerances that include insulation and installation space. Group conflicts by structural element rather than by service: the structural engineer will have to approve them.

03

Formal decisions

For each structural conflict, compare three options: reroute the service, create an approved opening, or modify the element. The decision is written down with its programme and cost impact.

Warning signs

  • Builder’s work drawings arriving after the pour date.
  • A structural engineer not invited to coordination meetings.
  • Ducts sized at construction stage far beyond design assumptions.

This interface is at the heart of our MEP and all-trades coordination and BIM coordination services.

04 —

Let’s talk about your project

Preparing the construction stage of a services-intensive project? Tell us about it through our contact form: you will be contacted within 24 hours, and a commercial proposal can be sent within 48 hours of receiving your input data.

Chat on WhatsApp